Back to Alternative Networks Homepage
October 1999

Alternative Networks
Cyprus
Update Memo

The following report outlines new developments in the past three months and the state of on-going developments.

The following document summarizes the current developments in the plans of the Electricity Authority of Cyprus (E.A.C.) for the enhancement of their alternative network. As mentioned in the Master Report, no other public utility organization is currently involved in the development or usage of an alternative telecommunications network.

1. Historical Background

The Electricity Authority of Cyprus is currently the only Public Utility Organization which has developed and is using an alternative communication network. The said system makes use of the Power Line Carrier network which carries information by using fiber optics communication links through the use of mainly its overhead and secondly its underground network ; and underground pilot networks. The Cyprus telecommunications Authority positioned itself in a sympathetic way towards the alternative network of the E.A.C,, even though no cooperation in this particular field has been reported.

2. Current Developments

According to the management of the E.A.C., it is the Authority’s decision to expand its alternative network, focusing on fiber optics technology, and towards this end, engineering teams have been working in designing and constructing additional parts of it.

The underlying objectives of the said network would be to :

The envisioned alternative network comprises 3 phases, as follows :

In line with the above-mentioned objectives, the Authority has fully integrated fiber optic cables in 9 existing high voltage transmission lines, their total length being 140 Km. Furthermore, the integration of fiber optics cables in the remaining 3 high voltage transmission lines (of a total length of 82 Km) is currently being implemented.

Phase 2 is scheduled to be completed within the next 3 years, with a total length of fiber optics cable of 105 km being integrated in new transmission lines. Subsequently, the network would be in a position to face the competition emerging from the anticipated deregulation of the market.


Please note that this report has been prepared under the sole responsibility of the
ESIS II contractors.
It does not necessarily reflect the views of the Commission, nor does the Commission accept responsibility for the accuracy or completeness of information contained herein.
The ESIS Team of contractors welcomes any additional information or corrections.

 

navigation2.jpg (7319 octets)